As electric vehicles (EVs) become more popular, the need for reliable and accessible charging stations is growing. If you’re planning to install an EV charging station in Glendale Heights, Illinois, it’s important to follow local regulations and safety standards. This guide outlines the key steps:
1. Permitting Process
Before installation, you must obtain the proper permits from the Community Development Department.
Where to Apply:
- In Person: 300 Civic Center Drive, Glendale Heights, IL 60139
- By Mail, Fax, or Email:
- Fax: 630.260.1317
- Email: permits@glendaleheights.org
Who Can Apply:
- Property owners or authorized contractors registered with the Village.
Required Documents:
- Site plan
- Electrical drawings
- Load calculation sheet
- HOA approval letter (if applicable)
- Engineer/architect seal (if project cost exceeds $10,000)
2. Electrical Load Calculations
Load calculations ensure your electrical system can support the EV charger.
Charger Types:
- Level 1 (120V): Minimal load; no permit needed if using existing outlets.
- Level 2 (240V): Requires a permit and load calculations.
Load Calculation Sheet Must Include:
- Size of existing service panel
- Existing electrical load
- Proposed load from EV charger
- Circuit breaker size
- Conductor types and sizes
- Conduit specifications
3. Electrical Drawings
These are required for permit approval and safe installation.
Include the Following:
- Single-line diagram (power source, circuit breaker, conduit/wiring path, charger location)
- Site plan (parking layout, charger mounting height, ADA compliance if public access)
- Manufacturer specifications for the EVSE (Electric Vehicle Supply Equipment)
4. Electrician Registration & Bonding
Electricians must be registered with the Village to perform work.
Who Must Register:
- Any electrician or electrical contractor working in Glendale Heights.
Required Documents:
- Completed Contractor Registration Application
- $20,000 Surety Bond (Plumbing contractors exempt)
- Valid electrical license from an approved municipal corporation
Fees:
- Registration Fee: $75
- Fee Waiver: Available for electricians with a valid municipal license
Submit Registration:
- In Person: Community Development Department
- By Email: permits@glendaleheights.org
- By Fax: 630.260.1317
Final Tips
- Start Early: Permit approval may take up to 14 days, especially if revisions are needed.
- Hire Licensed Professionals: Ensure your contractor is registered with the Village.
- Plan for Expansion: Consider installing EVSE-ready infrastructure for future scalability.